Budgets

Business AS · Finance and accounting. The idea in plain words, the rules to remember, the mistake to avoid and a worked example, written and checked by Mega Lecture.

Test this topic freeAll Business AS topics

The idea

A budget is a detailed financial plan for a future period, with targets for revenue, costs or output. Budgets share out resources between departments, give managers targets, and let the business control and monitor spending by comparing actual results with the plan.

Budgets can be set in different ways. An incremental budget takes last year's figure and adjusts it. A flexible budget changes with the actual level of output. Zero budgeting starts each budget at nothing, and every item of spending must be justified.

A variance is the difference between a budgeted figure and the actual figure. What matters is the effect on profit: favourable if profit is higher than planned, adverse if it is lower.

In simpler words

A budget is a money plan for the months ahead. Budgets share out money, give managers targets, and let the business check spending against the plan. They can be set by adjusting last year's figure, by starting from zero and justifying every item, or by changing with output. A variance is the gap between plan and reality.

An everyday comparison

A budget is like a family's monthly spending plan. If the food bill comes in under plan, that is favourable; if the electricity bill comes in over, that is adverse. If a parent earns more than planned, that is favourable too. The rule is always 'what does this do to the money left over?' The comparison stops there: a business also uses budgets as targets, and a bad target can make staff spend wastefully to use it up.

Rules to remember

Common mistake

Students call every "actual higher than budget" result favourable. For costs it is adverse, because higher costs reduce profit. Always ask what the difference does to profit.

In the exam

For a calculation, write variance = actual − budgeted, substitute, then label it F or A by its effect on profit: revenue above budget is favourable, cost above budget is adverse. For a flexible budget, first flex the cost to actual output (budgeted cost per unit × actual output) before comparing. For written answers, define the budget type, give one benefit and one drawback, apply to the case (for example, incremental budgeting carries past waste forward), and judge whether the budget helps or harms motivation here.

Worked example

Budgeted revenue was $200,000 and actual revenue was $212,000. Budgeted costs were $150,000 and actual costs were $165,000. Find each variance and the profit variance.

  1. Revenue variance = 212,000 − 200,000 = $12,000 favourable (more revenue than planned).
  2. Cost variance = 165,000 − 150,000 = $15,000 adverse (more cost than planned).
  3. Budgeted profit = 200,000 − 150,000 = $50,000; actual profit = 212,000 − 165,000 = $47,000.
  4. Profit variance = 47,000 − 50,000 = $3,000 adverse (also 12,000 F − 15,000 A).

Answer: Revenue $12,000 favourable, costs $15,000 adverse, profit $3,000 adverse.