A factory has two cost pools: machine set-ups $60 000 (40 set-ups in total) and inspection $36 000 (900 inspections in total). Product X uses 25 set-ups and 300 inspections, and 10 000 units are made. What is the overhead cost per unit of X under ABC?
- Set-up rate = $60 000 ÷ 40 = $1500 per set-up; inspection rate = $36 000 ÷ 900 = $40 per inspection.
- Overhead for X = (25 × $1500) + (300 × $40) = $37 500 + $12 000 = $49 500.
- Overhead per unit = $49 500 ÷ 10 000 = $4.95.
Answer: The overhead cost of product X is $4.95 per unit.