The standard for one unit is 2 labour hours at $12 per hour. Actual output was 1500 units. The workers took 3150 hours and were paid $36 225. Calculate the labour rate and efficiency variances.
- Rate variance = (3150 hours × $12) − $36 225 = $37 800 − $36 225 = $1575 favourable.
- Standard hours for actual output = 1500 × 2 = 3000 hours.
- Efficiency variance = (3000 − 3150) × $12 = −$1800, so $1800 adverse.
- Check: standard cost 3000 × $12 = $36 000; actual $36 225; total $225 adverse = $1575 F − $1800 A.
Answer: Labour rate variance $1575 favourable; labour efficiency variance $1800 adverse.